Notifying Minor Construction in 2026: What Qualifies, Form and Process

Notification of minor construction is a simplified approval process for smaller construction projects under §55 of Act No. 50/1976 Coll. (the Building Act). It applies to minor structures with an area up to 25 m² and a height up to 5 m, fences, utility connections, and wells up to 100 m deep. The building authority has 30 days to respond—if it does not, you can begin construction. The fee is EUR 30 for an individual and EUR 50 for a legal entity. A 50% discount applies for electronic filing via slovensko.sk.

Reading time: 5 min

What is minor construction

Minor construction refers to a smaller project that does not require a full building permit by law. It is sufficient to notify the building authority, which will either take no action (allowing you to proceed with construction) or determine within 30 days that a building permit is required.

A minor structure is defined in Section 139b(7) of the Building Act as a one-storey structure with a built-up area of up to 25 m² and a maximum height of 5 m that serves an ancillary function to the main building on the plot.

The notification process also applies to fences, utility connections, wells up to 100 m deep, and certain other structures listed in §139b and §55.

What qualifies as minor construction

Yes

Garden shelter, gazebo, pergola

Area up to 25 m², height up to 5 m, not for permanent residence. Open or semi-open structures.

Yes

Garage up to 25 m²

A single-car garage as an ancillary structure to a house. A building permit is required for larger areas.

Yes

Garden shed, storage unit

A wooden or masonry shed in the garden for tools or bicycles. Area up to 25 m².

Yes

Pool up to 25 m²

An outdoor pool with a built-up area of up to 25 m² and a depth of up to 3 m. A building permit is required above this limit.

Yes

Fencing

A fence around the property, gate. Additional conditions may apply for heights over 1.8 m or in a protected zone.

Yes

Utility connections

Connection of water, gas, electricity, and sewerage from the public grid to the property. Requires a statement from the utility provider.

Yes

Well up to 100 m

A drilled well for a house or garden use. Also requires a permit from the water company.

No—permit required

Structure over 25 m² or 5 m

Any structure exceeding these limits requires a building permit.

Notification process

The notification process usually takes 30–45 days, including the building authority's waiting period.

  1. 01

    Download the form from the municipality's website

    Each town has a form titled "Ohlásenie drobnej stavby / stavebných úprav a udržiavacích prác" (Notification of Minor Construction / Building Modifications and Maintenance Work). You can usually find it in the Building Authority or Forms section.

  2. 02

    Fill in the basic information

    Builder's identification; description of the structure (type, dimensions, materials, use); location (by title deed number, cadastral parcel, and cadastral area); and the planned start and completion dates.

  3. 03

    Prepare the attachments

    Simple site documentation (floor plan, site plan showing the location on the lot to scale). You can prepare this yourself for simple structures; for more complex ones, we recommend hiring a designer. Title deed for the lot. Statements from the relevant authorities for utility connections (water, gas, and electricity suppliers).

  4. 04

    Consent of co-owners

    If the parcel is under co-ownership or marital community property, you need the consent of all co-owners (or the other spouse in the case of marital community property) for the notification.

  5. 05

    Filing with the building authority

    In person at the office, by registered mail, or electronically via slovensko.sk. There is a 50% discount on the fee for electronic filing.

  6. 06

    Payment of the fee

    Administrative fee of EUR 30 for natural persons, EUR 50 for legal entities, paid in cash at the filing office or by bank transfer. The electronic fee is EUR 15 / EUR 25.

  7. 07

    Wait 30 days

    The building authority has 30 days from the filing date to respond. It can either: (a) take no action – after 30 days, you can start construction, (b) issue a written decision that a building permit is required, or (c) reject the notification.

  8. 08

    Construction

    After the 30-day period has passed (or after receiving explicit consent from the authority), you can begin construction. The structure must be completed within 2 years of the notification.

Fees and deadlines

ActionFeeDeadline
Notification – paper (natural person)EUR 3030 days
Notification – electronic (natural person)EUR 1530 days
Notification – paper (legal entity)EUR 5030 days
Notification – electronic (legal entity)EUR 2530 days
Extension of notification validityEUR 20-

Source: Act No. 145/1995 Z. z. on administrative fees, item 60(e).

Difference from a building permit

Key differences between a notification and a building permit:

  • Form of decision. With a notification, the authority's silence implies consent, or it can actively require a permit. With a building permit, it always issues a written decision.
  • Deadline. Notification: 30 days. Building permit: 30–60 days for the administrative procedure, plus additional weeks for statements from other bodies.
  • Parties to the procedure. With a notification, there is no hearing, and neighbors have no right of appeal. With a building permit, they are parties to the procedure and can appeal within 15 days.
  • Fee. EUR 30 for a natural person vs. EUR 50 for a natural person for a building permit (for a house).
  • Project documentation. For a notification, a site plan and description are sufficient. A building permit requires a comprehensive project from a licensed designer.
  • Final building approval. Minor structures are not subject to final building approval. Once the work is finished, you only need to notify the building authority. Final building approval is mandatory for projects that require a building permit.

Common mistakes

  • Starting construction before the 30-day period expires. Even for a minor structure, the building authority has 30 days from the date of notification to decide that a permit is required. Starting earlier constitutes unauthorized construction.
  • Exceeding the 25 m² built-up area. Exceeding the limit by even 0.5 m² means a building permit is required. The building authority will measure the dimensions during an inspection.
  • Building in a protected zone without consent. If you are building near water, gas, or electricity lines within a protected zone, you need the consent of the utility network operator.
  • Building without a co-owner's consent. In cases of co-ownership or marital community property, the consent of the other party is mandatory.
  • Building intended for permanent residence. A 'minor structure' cannot be a habitable space. A mobile home that you convert for residential use is considered a building and requires a building permit.

Frequently asked questions

A notification is for minor structures up to 25 m² and 5 m in height. The authority has 30 days to respond; if it does not, you can start building. A building permit is a formal decision issued by the authority for larger structures and requires official proceedings, full project documentation, and a final building approval.

30 days from submission. If the authority does not respond within this period, it is considered tacit consent, and you can start building. However, if it sends a notice that a building permit is required, you must follow the full permit application process.

The administrative fee is EUR 30 for a natural person and EUR 50 for a legal entity. For electronic submissions via slovensko.sk, there is a 50% discount (EUR 15 / EUR 25).

Yes, if it is a permanent structure fixed to the ground (on point or slab foundations). A mobile stall that is not anchored and can be easily moved is not considered a structure, and notification is not required.

A permanent pool with a built-up area of up to 25 m² is notified as a minor structure. A building permit is required for pools over 25 m² or deeper than 3 m. An above-ground vinyl pool that does not involve construction work is not considered a structure.

No. Minor structures do not undergo final building approval. Upon completion, you only need to notify the building authority that the structure is finished. However, property tax also applies to minor structures, so do not forget to file a tax return.

Yes, via the slovensko.sk portal using a national ID card with an electronic chip (eID). Electronic submissions receive a 50% discount on the administrative fee.

2 years from the date of submission. You must start construction within this period and finish it within a reasonable time. An extension can be requested by submitting a new application (EUR 20).